Muckhart Village from Seamab

Blairhill: Notice of Timber Operations

MCC has been advised by the landowner that work is due to commence on timber operations, in the area of the SSSI at Blairhill, at the beginning of next week, depending on the weather at this time.

The felling operation should take about two weeks to complete and the subsequent timber transport operations are due to start early in November. All operations should be complete by the middle of the month. The operator has been advised about the school start and finish times and transport operations will take place out with these times.

Following the completion of these operations, the landowner will ensure the track is restored.

 

Mike Wilson

Secretary – Muckhart Community Council