H49 Development Latest Update

Yesterday, MCC received a brief update from Springfield regarding upcoming site activities on H49.

On Monday (11th October) preliminary work will commence on-site, including the installation of the security (heras) fencing around the site boundary and the setting up of a temporary compound.

On the following Monday (18th October) work will commence on forming the new access from the A91, as approved by the Council.

 

Mike Wilson

Secretary – Muckhart Community Council